CIVIL TECHNOLOGY:CONSTRUCTION GRADE 12 NATIONAL SENIOR CERTIFICATE EXAMINATIONS MAY/JUNE 2021
Markers should:
Familiarise themselves with the question and answer before evaluating the responses of candidates.
Always interpret the responses of the candidates within the context of the question.
Consider any relevant and acceptable answer during pre-marking but should strictly adhere to the answers after finalisation of the marking guideline.
There are two approaches to answering questions, these are (1) to describe and (2) to explain.
If a candidate is required to explain e.g., a process in 4 steps, only the first 4 responses should be considered.
If, however a candidate is required to e.g., explain or describe how to transfer heights from one point to another using a transparent pipe level we need to consider that candidates may write a long description not necessarily well organised as an intellectual response may do. In this case the marker needs to evaluate the complete statement to judge if the candidate explained the required outcome satisfactorily and allocate marks on merit. The marker should apply his/her professional judgement with these types of questions.
Mark what the candidate wrote and do not award marks for answers that the marker thinks the candidate meant with what was written.
Indicate the tick or cross right at the position where the mark needs to be awarded or where the candidate made the error.
Accept the letter corresponding with the correct answer as well as the answer written in full in multiple-choice questions.
Accept incorrect spelling in one-word answers unless the spelling changes the meaning of the answer.
For calculations:
A mark is only awarded if the correct unit is written next to the answer.
If TWO marks are awarded ONE mark is awarded for the answer and ONE mark for the correct unit.
Where the candidate made a principle error e.g. added instead of multiplying, no marks will be awarded for the steps. If the answer is correct according to what the candidate did, the mark for the answer can be awarded for the application of skills.
Where an incorrect answer could be carried over to the next step, the first answer will be deemed incorrect. However, should the incorrect answer be carried over correctly, the marker has to recalculate the values, using the incorrect answer from the first calculation. If correctly used, the candidate should receive the full marks for subsequent calculations.
Markers should consider when and where a candidate has rounded off in a calculation, as well as the subsequent effect it has on the final answer obtained. The calculation should therefore be awarded marks on merit.
Alternative methods of calculations must be considered, provided that the correct answer is obtained.
When marking drawings:
The member for which the mark should be awarded should be drawn correctly in the correct position to receive a mark.
A member incorrectly drawn but wrongfully repeated in another position will be awarded the mark for the repeated incorrect member provided that the marking guideline provide for TWO or more marks for that member (positive marking).
Marks can only be awarded for a label if the label is correctly indicating the correct member.
Scale drawings should always be marked using an appropriate mask.
When a candidate drew the wrong drawing e.g.:
A horizontal section instead of a vertical section, no marks will be allocated to the drawing as the candidate did not respond to the expected outcome.
An orthographic view instead of sectional view, no marks will be allocated to the drawing as the candidate did not respond to the expected outcome.
An orthographic view instead of an isometric view, no marks will be allocated to the drawing as the candidate did not respond to the expected outcome.
If the incorrect drawing was drawn, the candidate can be awarded for only what was asked but mark/s for the correctness of the drawing will not be awarded e.g., if a King Post roof truss was asked in the question, and candidate drew SA-Howe Truss.
QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS AND EQUIPMENT AND JOINING (GENERIC)
Use of bolts and nuts/bolts, washers and nuts will ensure that parts are secured tightly together, which is not always possible with screws.
Can easily be removed. ANY ONE OF THE ABOVE (1) [20]
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
NO.
QUESTION
ANSWER
MARKS
1
Identify the type of plan in FIGURE 2.
Site plan ✓
1
2
Deduce from the notes the brick force installation up to window height.
Every third course ✓
1
3
Deduce the scale that is used for FIGURE 2.
1 : 200 ✓
1
4
Identify number 1.
Boundary line ✓
1
5
Identify number 3.
Building line ✓
1
6
Identify number 5.
Main sewer line/Sewer line ✓
1
7
Identify number 7.
Entrance/Driveway ✓
1
8
Identify number 8.
Municipal sewer connection/Municipal Manhole/Manhole ✓
1
9
Identify number 9.
North/North symbol/direction/point ✓
1
10
Name the item in the column for the notes in FIGURE 2 that must be installed in the bathroom.
Shower ✓
1
11
Draw the electrical symbol as described in the column for the notes in FIGURE 2
✓✓
2
12
Deduce from FIGURE 2 which company printed the building plan.
Henson Printers ✓
1
13
Give the abbreviation for number 2.
RE ✓
1
14
State the colour that you would use to indicate the new dwelling on the site plan.
Red ✓
1
15
Deduce from FIGURE 2 why the new dwelling is to be built on a corner plot.
No plot on eastern side ✓
Quarter rounding at the corner of the pavement
Paving on the eastern side
Street on the eastern side ANY ONE OF THE ABOVE
1
16
Deduce the plot number of the new dwelling illustrated in FIGURE 2.
51 ✓
1
17
Which elevation is the closest to Protea Street?
South elevation✓
1
18
What is the plot number of the property on the western side of the dwelling?
49 ✓
1
19
Give the abbreviation for number 6.
MH ✓
1
20
State the slope at which the main sewer line should be installed.
1:40 ✓
1
21
Describe what was done as revision 1.
Rectify dimension ✓
1
22
Deduce the dimension fault on the total width of the dwelling.
100/14 100/14 000 mm ✓
1
23
State the project number for this plan.
GR 448 - 209 ✓
1
24
What is the width of the pavement?
1 500 mm or 1,5 m ✓
1
25
How many branch pipes are indicated on the plan?
5 ✓
1
26
Explain the purpose of number 4.
To give access to the sewer line when blockages occur/or for inspection purposes. ✓
1
27
In what SI unit are the dimensions indicated on the plan?
mm ✓
1
28
Draw a neat freehand drawing of the top view of the symbol of a single kitchen sink, as indicated in the SANS/SABS Code of Practice for Building Drawings.
3
29
Recommend TWO types of building materials that can be used to finish the area at number 7.
Bricks/Paving ✓ Tar ✓ Concrete slab/Gravel/Asphalt ANY TWO OF THE ABOVE
2
30
Calculate the total area of the plot. Give your answer in m². Show ALL calculations.
(35 m ✓ x 25 m ✓) = 875 m² ✓ OR (35 000 mm x 25 000 mm) = 875 m²
3
31
Calculate the distance between Number 1 and Number 3 on the north elevation. Show ALL calculations.
(10 000 mm ✓ - 3 000 mm ✓) = 7 000 ✓ mm ✓ OR (10 m - 3 m) = 7 m
4
TOTAL
40
QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)
The site must be cleared of all rubble and loose soil must be removed. ✓
The building site must be levelled. ✓
A baseline must be established. ✓ (3)
4.2.5 Atmospheric hazards:
Low oxygen ✓
Hazardous fumes ✓
Toxic gases ANY TWO OF THE ABOVE (2)
4.2.6 Provision must be made to exit the trench safely e.g. a ladder or scaffold. ✓ (1)
4.2.7
So that they do not endanger themselves or others. ✓ To avoid mistakes during excavations. So that the workers will have the knowledge to do the work correctly ANY ONE OF THE ABOVE (1)
4.3
4.3.1 Soleplate/Sleeper ✓ (1) 4.3.2 Bearer ✓ (1) 4.3.3 Cleats ✓ (1) 4.3.4 To level/raise/lower/stabilise the formwork. ✓ (1) 4.3.5 Support the base shutter board of the concrete floor slab. ✓ (1)
4.4 Shuttering/Formwork for:
a concrete beam ✓
a concrete beam with floor slab/a concrete beam with slab
a floor slab
staircases
columns ANY ONE OF THE ABOVE (1)
4.5 Uses of wedges in formwork:
The shape of the wedges simplifies the erection and dismantling of formwork. ✓
Wedges can easily be removed by knocking the one from the other. ✓
Raising/Lowering/Levelling of formwork. ANY TWO OF THE ABOVE (2)
4.6 42° ✓ (1)
4.7 Lining:
Plywood or any other suitable material is put inside the formwork to give a smooth finish. ✓✓ (2)
4.8 Pair of wedges/Folding wedges: (2)
4.9
4.9.1 Exposes the operator to vibrations.✓ (1) 4.9.2 Numbness may occur ✓ (1) 4.9.3 If parts of the machine are not cleaned:
the concrete will harden on all parts. ✓
the hardened concrete on the machine will have a negative impact on the working performance. ✓ (2)
4.10 A thin layer of oil will prevent rusting. ✓ (1) [40]
QUESTION 5: PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS MEANS OF COMMUNICATION (SPECIFIC) 5.1 Plaster/Skimming plasters ✓ (1) 5.2 Water will make the mixture more workable. ✓ (1) 5.3 1:3 ✓ (1) 5.4 Screed types:
Dry ✓
Monolithic
Bonded screed ANY ONE OF THE ABOVE (1)
5.5 The screed will breakup or crack. ✓ (1) 5.6 5 mm ✓ (1)
5.7 5.7.1 Weep hole:
It allows water that penetrate the outside wall to drain out. ✓
To prevent any moisture from entering the inner skin of the wall. ANY ONE OF THE ABOVE (1)
5.7.2 Position of the weep hole:
Above the horizontal damp-proof course ✓
External part in the wall.
In line with the concrete/floor slab.
On the same level as the floor slab. ANY ONE OF THE ABOVE (1)